| Particulars | Description | |
| Name of the Project | : | Hana Textiles Limited. |
| Date of established | : | 19 August 2014 |
| Location of the Project | : | Company: 337/A, Chanpara, P.o. Uttar khan, Dhaka-1230. Bangladesh. Factory Address: Basic Area, Plot # 20, Shibpur , Narshidhi, Factory -02: (ACTL) , Savar, Factory-03(SCTL) , Gazipur. |
| Area of land | : | Factory project Land: 7000 sft , Factory -02: (ACTL). Project land: 8,400 sft. Factory-03(SCTL). Project land: 66,000 sft. |
| Ownership of project land | : | The project name of the: Hana Textiles Limited. |
| Description of building | : | Factory still shit tin shed building each floor. Factory -02: (ACTL). & Factory-03(SCTL). Both factories building contraction are same. |
| List of machine | : | As below |
| Means of Finance | : | Bank Loan –Tk-0.00 Core ( 0.00 % ) Equity-TK=25.71 core (100.00 % ) |
| Working capital arrangement | : | Islami Bank Bangladesh Ltd. |
| Capacity of the project | : | Per day Production Capacity: per machine 50 kgs @ 110 LbS =1322 Pcs per Hour. (Towel Size-12X12-per pieces 37.83 Gm X 50 Kgs =1322 pcs per day (Towel Size-16X19-per pieces 70.93 Gm X 50 Kgs =704 pcs per day (Towel Size-16X27-per pieces 85.12 Gm X 50 Kgs =587 pcs per day (Towel Size-22X44-per pieces 217.54 Gm X 50 Kgs =230 pcs per day (Towel Size-24X48-per pieces 274.29 Gm X 50 Kgs =182 pcs per day (Towel Size-24X50-per pieces 397.25 Gm X 50 Kgs =125.86 pcs per day Total Production Capacity per Hour=(Per Machine 60 pcs x 180 Machine)=10800 Pcs or 1625.00 kgs /3582.48 Lbs Per Month Production : 1464650 Pcs or 338,000 Kgs/ 745,154.80 Lbs, Per Year Production :95,51,520 Pcs or 4,056,000 Kgs /8,941,857.6 Lbs |
| Required load for electricity | : | Factory Electricity : 2.00 MW Factory-02(ACTL) Electricity :3.00 MW Diesel Generator : 3.00 MW Factory-03(SCTL) Electricity :4.00 MW Gas Generator Capacity :3.5 MW |
| Source And arrangement of electricity | : | Electricity capacity Own Factory : Narshingdhi Bscic power sub stationa : Using Capacity 1.3 MW Saver Palli Bidet supplier company :1st Factory :using capacity 3.00 MW Gazipur palli biddut Company 2nd Factory : Using Capacity :4.30 MW |
| Source And arrangement of gas | : | Titas Transmission & Distribution company Limited, And diesel purchase by self from the nearest filling station. |
| Other Utility facilities | : | Water, Sewearage, Gas & other utility are available. |
| Present operational status | : | 90 % running in full swing & next 6 Month will be running full swing. |
| Manpower | : | Factory manpower : (Male-85 and Femel-25) Total-110 person Factory-02 (ACTL) Manpower : Male-348 and Femel-167) Total-515 person Factory-03 (SCTL) Manpower : Male-795 and Femel-278) Total-1073 person Grand Total= (Male-1228 & Femel-470 ) = 1698 person |